Question 1
25999

\(\text{In the adjacent network diagram,}\) 

\(\text{(i) What is the critical path? }\)

\(\text{(ii) If activity D is reduced to 2 days,}\)

\(\text{what is the new completion time?}\)

\(\text{(i) DE is critical path}\)

\(\text{(ii) 9 days}\)