Resources For Teachers For Tutors For Students & Parents AI New Pricing
Year 12 Maths Standard 2 (2027) Critical path analysis

Network Diagrams from Precedence Tables

ACCOUNT REQUIRED

Unlock all 20 questions & worked solutions

You're viewing a free preview. Create an account to access the complete question set, step-by-step solutions, and progress tracking.

All Questions

Access the full question set for every topic.

Worked Solutions

Step-by-step explanations for every answer.

Track Progress

Mark questions right or wrong and monitor your growth.

It's Free

No credit card required - sign up in under a minute.

Question 1
189707

In an activity-on-edge network the arrows are the activities and the numbered circles are the events. How many activities are in the project shown below?

Activity-on-edge networkCount the labelled arrows: six activities A-F. A 3 B 4 C 5 E 2 D 6 F 4 1 2 3 4 5 6
6
1 mark