Resources For Teachers For Tutors For Students & Parents AI New Pricing
Year 12 Maths Standard 2 (2027) Critical path analysis

Minimum Completion Time

ACCOUNT REQUIRED

Unlock all 20 questions & worked solutions

You're viewing a free preview. Create an account to access the complete question set, step-by-step solutions, and progress tracking.

All Questions

Access the full question set for every topic.

Worked Solutions

Step-by-step explanations for every answer.

Track Progress

Mark questions right or wrong and monitor your growth.

It's Free

No credit card required - sign up in under a minute.

Question 1
189787

A builder plans a backyard deck as the activity network below; each number is the duration of that activity, in days. The project is finished only when every activity is complete. What is the minimum completion time for the deck?

Backyard deck activity networkActivity-on-edge network, durations in days, find the minimum completion time. A 6 B 4 C 2 D 5 1 2 3 4
9
 \(\text{ days}\) 1 mark