Resources For Teachers For Tutors For Students & Parents AI New Pricing
Year 12 Maths Standard 2 (2027) Critical path analysis

Float Times & the Critical Path

ACCOUNT REQUIRED

Unlock all 20 questions & worked solutions

You're viewing a free preview. Create an account to access the complete question set, step-by-step solutions, and progress tracking.

All Questions

Access the full question set for every topic.

Worked Solutions

Step-by-step explanations for every answer.

Track Progress

Mark questions right or wrong and monitor your growth.

It's Free

No credit card required - sign up in under a minute.

Question 1
189767

The network shows the tasks for setting up a community festival stage; each activity is labelled with its letter and duration in days. Each event circle shows the event number (top), its earliest start time EST (lower-left) and its latest start time LST (lower-right). What is the float time of activity \(D\)?

Festival stage networkActivity-on-edge network with EST and LST at each event. A 3 B 5 C 4 D 5 E 2 1 0 0 2 3 3 3 7 7 4 9 9
1
 \(\text{ day}\) 1 mark